YMCA addition hits milestone

By Jordan Beck 2 min read
Jordan Beck | Daily Press An athletic addition to the Northern Lights YMCA building — home to Bay College’s gymnasium facility — is pictured. Work on this addition has been impacted by this winter’s severe winter weather.

ESCANABA -- Work on an athletic addition to the Northern Lights YMCA building -- home to Bay College's gymnasium -- has been impacted by the severe weather this winter.

The work currently taking place at the Northern Lights YMCA building is being done to complete the project's first phase. This phase will include locker rooms for the Bay College Norse, away teams, coaches and referees; a training facility; and offices.

The project hit a major milestone recently.

"The roof is on, and they have sealed up the building," Bay Vice President of Operations Christine Williams said.

Work finishing the inside of the facility was not able to begin immediately after the building was sealed.

"Now they're in the process of warming the building up," Williams said.

This is necessary so the ground inside the building can be thawed.

Bitterly cold temperatures and heavy snowfall have affected work on the addition to the Northern Lights YMCA building in other ways, as well.

"This has been a very challenging winter to have a winter project," Williams said.

Williams said the date of the first phase's expected completion has been pushed back.

"It looks like we're about three to four weeks behind schedule," she said.

She noted this should not have a financial impact on Bay or the contractors working on the project.

"There's no increased cost to us -- it's just a delay in time," Williams said.

Responses to a request for proposal (RFP) related to the project were opened Thursday.

"That's for the electrical work," Williams said. Four bids were received for the work; the contract was won by N K Electric of Escanaba with a total bid of $59,452.

Submissions for the final RFP released for the project's first phase, which is focused on interior finishes, are due by 1 p.m. on March 27.

"That'll be doors and (trim) and carpet and flooring," Williams said.

Submissions for an RFP focusing on lockers in the new facility are due by April 5. This RFP was released before the RFP focusing on interior finishes, but includes a longer amount of time for interested parties to respond.

According to Williams, the project's first phase should be finished midway through summer.

"It's not going to be until mid- to the end of July," she said.