Road, bridge repairs scheduled over summer months
Trending
ESCANABA -- Several major road and bridge repair projects will be taking place in the area over the coming months.
Many of the projects will be undertaken by the Michigan Department of Transportation (MDOT). In Delta County, MDOT's largest project involves the replacement of the U.S. 2 and 41 bridge over the Escanaba River. This project began last spring.
Dan Weingarten, MDOT communications representative for the Superior Region, said this project is expected to be finished in late September.
"(It) will be wrapping up this year," he said.
MDOT will also begin working on the reconstruction of U.S. 2 and 41's westbound lanes between Gladstone and Rapid River next month.
"That's a project that we expect to start in June," Weingarten said. It is expected to last through September, and will cost an estimated $6.2 million. One lane will be open in each direction during work on the project.
The other half of this project will begin at a later date.
"The eastbound lanes will be reconstructed in 2020," Weingarten said.
Other work MDOT plans to do in Delta County includes the resurfacing of 2.4 miles of U.S. 2/41 in Escanaba from North 30th Street to Danforth Road (which should take place through Sept. 14 at an estimated cost of $800,000 with lane closures, traffic shifts, and an 11-foot width restriction in the work zone) and the resurfacing of 16 miles of asphalt on M-35 from the Menominee County line to the Delta County Airport (which should last from July to October at an estimated cost of $2.6 million with one lane open in alternating directions under flag control).
MDOT will not be the only organization hard at work on roads in Delta County this year. The Delta County Road Commission (DCRC) will also be working on a variety of projects.
DCRC Manager Jody Norman said one of the commission's most significant projects will be the replacement of the Country Road 430 bridge over the Escanaba River.
"That's a complete bridge replacement," Norman said. Work on this bridge, which started Monday, will cost an estimated $1.4 million. The contractor for this project is Lunda Construction Co.
The bridge will be shut down until the project's completion (which is estimated for September), Norman said. In the meantime, signage for a detour route has been put into place.
The DCRC also plans to work on a smaller bridge -- the Beaver Lane bridge over the Days River in Perkins.
"Our crews will be doing that," Norman said. This project is expected to cost about $135,000; it is scheduled to start in late August and last for about five days.
In addition to this work, Norman said the DCRC will be doing quite a bit of paving in the coming months.
"We've got a fair amount of paving going," he said. This will include paving streets on the north and south sides of Rapid River at an estimated cost of $180,000, paving 2.5 miles of County Road 428 at an estimated cost of $162,000, paving two miles of County Road 416 at an estimated cost of $250,000, paving 1.3 miles of County Road 414 at an estimated cost of $325,000, paving one mile of C-17 at an estimated cost of $98,000, paving roads in Brampton Township at an estimated cost of $84,500, and paving Portage Point at an estimated cost of $83,000.
The DCRC will also work on about 75 miles of seal coating in the county (at an estimated cost of $1.3 million) and do about 20 miles of gravel road work (at an estimated cost of $400,000).
Along with these projects, the DCRC plans to work with the U.S. Forest Service and the State of Michigan to clear 18 miles of right-of-way on Highway 13. The northern portion of this work includes private parcels along the highway; in these areas, wood will be left along the highway for property owners.
Norman said the DCRC has asked that nobody else remove this wood.
"We're pretty concerned that people will be taking the wood for campfires or winter heating … purposes," he said.
A significant amount of road work will be done by MDOT in Schoolcraft and Alger counties this year, Weingarten said.
"We'll be doing a lot of work (on) M-94 in various locations," he said.
One particularly long stretch included in this work is over 22 miles long. This stretch runs from the Alger/Schoolcraft county line to Dodge Lake Road north of Manistique.
"This will be … a (double) chipseal project," Weingarten said. It is expected to cost $2.4 million, and will require single-lane closures.
Other MDOT work in Schoolcraft County will include the milling and resurfacing of 16 miles of M-94 north of Manistique (and three other locations in Alger and Schoolcraft counties, at a cost of about $2.2 million with single-lane closures), three miles of milling and asphalt overlay on U.S. 2 from Manistique River Bridge to Tannery Road (at an estimated cost of $668,000 with one lane open in alternating directions under flag control and an 11-foot width restriction in the work zone), and the milling and resurfacing of 10 miles of U.S. 2 from Gulliver to east of M-77 (at an estimated cost of $2.6 million).
MDOT does not plan to do a great deal of work in Menominee County in the near future. However, some work is planned for this area.
"We're actually doing two bridges as part of the same project … because the work being completed is similar (for) both bridges," Weingarten said. Work on the U.S. 2/41 bridge over Ford River near Hyde in Delta County started this month and is expected to be completed in late June. When this is done, work on the M-35 bridge over the Big Cedar River in Menominee County is scheduled to start. Both of these projects involve replacing pins and hangers, painting, and deck patching. On both bridges, one lane will be open in alternating directions with temporary traffic signals.
Weingarten noted that work on both of these bridges is expected to cost a combined total of $1.2 million, and the project should be done by early October.
For more information on MDOT road projects, visit michigan.gov/drive.