WELLS -- Current water levels on the Escanaba River have affected work on the U.S. 2 and 41 bridge over the river, Michigan Department of Transportation Communications Representative for the Superior Region Dan Weingarten said.
"The high water levels on the Escanaba River have prevented further progress on the piers," he said.
According to Weingarten, the piers have to be completed before bridge beams can be placed. A one-day bridge closure had been planned to allow for the placement of these beams.
"As a result, the beam placement … and the detour that we were planning for that phase have also been delayed," he said.
Previously, this closure had been scheduled for mid-May.
"Now, we're looking at potentially mid-June," Weingarten said.
When the closure does take place, eastbound traffic will be detoured from U.S. 2 via County Roads 426, 420, and 531 and onto M-35 before returning to U.S. 2. This route will be reversed for westbound traffic.
Despite this setback, Weingarten said work on the bridge has not stopped.
"In the meantime, crews are continuing to work on the bridge abutments," he said.
He also noted this situation should not delay the project's completion, which is still set for this fall.
"It's early enough in the construction season that we hope the contractor can make up that time going forward," Weingarten said. The project's prime contractor is Zenith Tech.
Since there are still several months of construction left before the bridge project is completed, Weingarten reminded drivers in the area to stay safe.
"As summer starts and travel picks up … it's important to drive slow in construction zones," he said.